Yemen LNG at a Glance
|
| Gas Supply |
Block 18 (Marib), central Yemen |
| Sales Gas Reserves |
9.15 TCF proven, 0.7 TCF Probable (1 TCF reserved for domestic market) |
| Plant Location |
Balhaf, Yemen (200 km SW of Mukalla, 320 km from Marib fields) |
| Number of Trains |
2 |
| Technology |
APCI C3/MCR (recognised international technology) |
| Total Capacity |
6.7 Mmtpa guaranteed capacity |
| Sales Contracts |
3 long-term contracts to GDF-Suez, Kogas and Total Gas & Power for a total of 6.7 Mtpa |
| Terminal |
Balhaf (dedicated) |
| Jetty Dimension |
70,000 - 205,000 m3 ships |
| Storage Tank Capacity |
2 x 140,000 m3 |
| Production Phase |
2009 |
|
TCF: Trillion Cubic Feet
Mmtpa: Million Metric Tonnes Per Annum |
|
|
|
|
|
|
|