22 February 2010The Performance Test of Train 1 has been successfully completed. This is another major milestone for Yemen LNG to celebrate. The Performance Test was conducted to demonstrate Train 1 capability of producing LNG as per design. For performance testing, during 72 hours the Train must continuously produce LNG at a rate not lower than the design value with a defined refrigerant composition. The test was performed by Yemen LNG Operations team and supervised by a team from APCI, Elliott and YEMGAS.